Timeline


  • Day 255/ 210 Days –>  Wed, 29th Jun’16:  Clarendon House Handover!
  • Day 254/ 210 Days –> Tue, 28th Jun’16:  Site & House Cleaning, completion of painting and final touches
  • Day 253/ 210 Days –>  Mon, 27th Jun’16:  Installation of appliances (Gas Stove, Rangehood, Microwave and Dishwasher), installation of continuous flow gas system
  • Day 250/ 210 Days –> Fri, 24th Jun’16:  Practical Completion Walkthrough
  • Day 249/ 210 Days –> Thu, 23rd Jun’16:  House cleaning and bricks and mortar fix-ups
  • Day 248/ 210 Days –> Wed, 22nd Jun’16:  Internal and External Painting completed, Front porch finishing completed
  • Day 247/ 210 Days –> Tue, 21st Jun’16:  Painting on full steam ahead, external double stacker doors & sliding door finishing completed, bed 1 external window corner finish completed, Alfresco painting and final external painting, Front porch ceiling painting
  • Day 246/ 210 Days –> Mon 20th Jun’16:  Final painting and touch ups, perimeter fence was taken down!
  • Day 245/ 210 Days –> Sun, 19th Jun’16:  Touch up and fix up before final painting
  • Day 244/ 210 Days –> Sat, 18th Jun’16:  No Visible Activity
  • Day 243/ 210 Days –> Fri, 17th Jun’16:  Rain garden completed
  • Day 242/ 210 Days –> Thu, 16th Jun’16:  Kitchen splashback installed, Carpet Installed, timber laminate installed on stairs & understairs.
  • Day 241/ 210 Days –> Wed, 15th Jun’16:  No Visible Activity
  • Day 240/ 210 Days –> Tue, 14th Jun’16:  No Visible Activity
  • Day 239/ 210 Days –> Mon, 13th Jun’16:  No Visible Activity
  • Day 236/ 210 Days –> Fri, 10th Jun’16:  Rainwater tank installation and connection
  • Day 235/ 210 Days –> Thu, 9th Jun’16:  Rainwater tank delivery, finishing and painting of external windows at the front
  • Day 234/ 210 Days –> Wed, 8th Jun’16:  No Visibile Activity
  • Day 233/ 210 Days –> Tue, 7th Jun’16:  Skirting Re-Installed & Carpet Delivery
  • Day 232/ 210 Days –> Mon, 6th Jun’16:  Front Porch Bricks Mortar Fixed Up
  • Day 230/ 210 Days –> Sat, 4th Jun’16:  Flooring Installation Continued
  • Day 229/ 210 Days –> Fri, 3rd Jun’16:  Flooring Installation Continued & Mirrors and Shower Screens Installation
  • Day 228/ 210 Days –> Thu, 2nd Jun’16:  Flooring Installation, Porch Pergola & Alfresco Eaves
  • Day 227/ 210 Days –> Wed, 1st Jun’16:  Flyscreens Installation
  • Day 226/ 210 Days –> Tue, 31st May’16:  No Visible Activity
  • Day 225/ 210 Days –> Mon, 30th May’16:  No Visible Activity
  • Day 222/ 210 Days –> Fri, 27th May’16:  No Visible Activity
  • Day 221/ 210 Days –> Thu, 26th May’16:  Replaced Window Skirting Installed
  • Day 220/ 210 Days –> Wed, 25th May’16:  Data and Security Works
  • Day 219/ 210 Days –> Tue, 24th May’16:  Internal and External Light Points and Top Floor Electrical Works, External Laundry Door Replacement, Installation of all Internal and External Door Handles, Installation of Toilet Fixtures, Replacement of Family Room Window
  • Day 218/ 210 Days –> Mon, 23rd May’16:  Electrical Works Commenced (Light Switches, Power Points both internal & external, Aircon Ducts, Aircon Panel)
  • Day 215/ 210 Days –> Fri, 20th May 2016:  Internal painting completed, external painting completed (downpipes, rendered facade and front pivot door)
  • Day 214/ 210 Days –> Thu, 19th May 2016:  Painting & Notice of Practical Completion 🙂
  • Day 213/ 210 Days –> Wed, 18th May 2016:  Painting, Painting & More Painting
  • Day 212/ 210 Days –> Tue, 17th May 2016:  Kitchen Sink, Toilet Suites, Basins, Bath Tub & Plumbing (Connected and Sealed Downpipes, External Taps Installed and Gas Continuos Flow Hot Water System Installed)
  • Day 211/ 210 Days –> Mon, 16th May 2016:  Painting, Benchtop & Garage Door
  • Day 208/ 210 Days –> Fri, 13th May 2016:  No Visible Activity
  • Day 207/ 210 Days –> Thu, 12th May 2016:  Sanding, Plastering & More Painting
  • Day 206/ 210 Days –> Wed, 11th May 2016:  No Visible Activity
  • Day 205/ 210 Days –> Tue, 10th May 2016:  Pulled Wires from Ceiling & Walls
  • Day 204/ 210 Days –> Mon, 9th May 2016:  Plastering and Sanding Continuation
  • Day 202/ 210 Days –> Sat, 7th May 2016:  Front Porch Ceiling, Gyprocking of Stairs & Patch & Sand Walls
  • Day 201/ 210 Days –> Fri, 6th May 2016: Cladding Painting
  • Day 200/ 210 Days –> Thu, 5th May 2016:  No Visible Activity 😦
  • Day 199/ 210 Days –> Wed, 4th May 2016:  No Visible Activity 😦
  • Day 198/ 210 Days –> Tue, 3rd May 2016:  Pivot Door Stain?
  • Day 197/ 210 Days –> Mon, 2nd May 2016:  Top Floor 1st Coat Painting & Tiling Continuation
  • Day 195/ 210 Days –> Sat, 30th April 2016:  Tiling and Lower Floor 1st Coat Painting
  • Day 194/ 210 Days –> Fri, 29th April 2016:  Top Floor Downpipes, Right Side Downpipes connection & Tiling
  • Day 193/ 210 Days –> Thu, 28th April 2016:  Painting, Tiles Delivery, Cabinetry & Vanities Installation
  • Day 192/ 210 Days –> Wed, 27th April 2016:  Kitchen Cabinetry & Bathroom Vanities Installation
  • Day 191/ 210 Days –> Tue, 26th April 2016:  Delivery of Kitchen Cabinetry & Bathroom Vanities
  • Day 190/ 210 Days –> Mon, 25th April 2016:  ANZAC Day Public Holiday
  • Day 187/ 210 Days –> Fri, 22nd April 2016:  No Visible Construction Activity 😦
  • Day 186/ 210 Days –> Thu, 21st April 2016:  Lower Floor Brick Clean, Skirting & Architraves Installation
  • Day 185/ 210 Days –> Wed, 20th April 2016:  No Visible Construction Activity 😦
  • Day 184/ 210 Days –> Tue, 19th April 2016:  Doors Installation & Locked Up!
  • Day 183/ 210 Days –> Mon, 18th April 2016:  Top floor Cornice Completion
  • Day 180/ 210 Days –> Fri, 15th April 2016:  Doors Installation Commenced
  • Day 179/ 210 Days –> Thu, 14th April 2016:  Ground Floor Corniced, Carpentry Materials Delivery
  • Day 178/ 210 Days –> Wed, 13th April 2016:  No Construction Activity 😦
  • Day 177/ 210 Days –> Tue, 12th April 2016:  No Construction Activity 😦
  • Day 176/ 210 Days –> Mon, 11th April 2016:  No Construction Activity :-(, Gyprock Scraps Picked Up
  • Day 174/ 210 Days –> Sat, 9th April 2016:  Stairs Installation
  • Day 173/ 210 Days –> Fri, 8th April 2016:  Wall Corners/ Edges Done
  • Day 172/ 210 Days –> Thu, 7th April 2016:  Sanding & @Clarendon Homes Email Response
  • Day 171/ 210 Days –> Wed, 6th April 2016:  Received Invoice $ Roof, Cladding & Gyprock Invoice $, No Activity 😦 ?
  • Day 170/ 210 Days –> Tue, 5th April 2016:  No Activity  😦 ?
  • Day 169/ 210 Days –> Mon, 4th April 2016:  Gyprock Jointing & Plastering Commenced!
  • Day 167/ 210 Days –> Sat, 2nd April 2016:  Gyprock installation commenced
  • Day 166/ 210 Days –> Fri, 1st April 2016:  Entire First Floor Internal Walls Insulated!
  • Day 165/ 210 Days –> Thu, 31st March 2016:  No Activity 😦 ?
  • Day 164/ 210 Days –> Wed, 30th March 2016:  Houspect Issues Addressed
  • Day 163/ 210 Days –> Tue, 29th March 2016:  Top & Lower Floor Insulation
  • Day 162/ 210 Days –> Mon, 28th March 2016:  Easter Monday Public Holiday
  • Day 160/ 210 Days –> Sat, 26th March 2016:  Aircon Rough In continued
  • Day 159/ 201 Days –> Fri, 25th March 2016:  Good Friday Public Holiday
  • Day 158/ 210 Days –> Thu, 24th March 2016:  Gyprock Materials Delivery, Cladding Installation
  • Day 157/ 210 Days –> Wed, 23rd March 2016:  Aircon Rough in and External Wiring
  • Day 156/ 210 Days –> Tue, 22nd March 2016:  Meet new @Clarendon_Homes Construction Area Manager and Pre-Lining Walkthrough with Site Manager
  • Day 155/ 210 Days –> Mon, 21st March 2016:  Lower Floor Scaffolding Stripped, Houspect Independent Pre-Lining Inspection, Right side perimeter fence stripped, External site cleaned
  • Day 152/ 210 Days –> Fri, 18th March 2016:  1st Stage of Waterproofing on all wet areas,  Installation of insulation on top floor commenced.  
  • Day 151/ 210 Days –> Thu, 17th March 2016:  Electrical  Cabling continued and Waterproofing commenced, Insulation Materials Delivery
  • Day 149/ 210 Days –> Tue, 15th March 2016:  Electrical Cabling
  • Day 148/ 210 Days –> Mon, 14th March 2016:  Data & Security Cabling, Bedding & Pointing of Lower Floor Roof Tiles
  • Day 145/ 210 Days –> Fri, 11th March 2016:  No activity 😦
  • Day 144/ 210 Days –> Thu, 10th March 2016:  Wall Weather Wrap Installation and Straightened Frames, Internal Site Clean
  • Day 143/ 210 Days –> Wed, 9th March 2016:  Cladding Materials Delivery
  • Day 141/ 210 Days –> Mon, 7th March 2016:  Lower Floor Terracotta Roof Tiles Installation
  • Day 138/ 210 Days –> Fri, 4th March 2016:  Lower Floor Roof Sarking Installation
  • Day 136/ 210 Days –> Wed, 2nd March 2016:  Lower Floor Roof Safety Rail Installation
  • Day 135/ 210 Days –> Tue, 1st March 2016:  Lower Floor Gutter & Fascia Installation
  • Day 134/ 210 Days –> Mon, 29th February 2016:  Lower Floor Roof Trusses Installation
  • Day 131/ 210 Days –> Fri, 26th February 2016:  Tidier Site
  • Day 130/ 210 Days –> Thu, 25th February 2016:  Top Floor Scaffolding Stripped
  • Day 128/ 210 Days –> Tue, 23rd February 2016:  Oxford Facade Rendering
  • Day 127/ 210 Days –> Mon, 22nd February 2016:  Top Floor Eaves and Downpipes Painting
  • Day 122/ 210 Days –> Wed, 17th February 2016:  Top Floor Downpipes Installation
  • Day 120/ 210 Days –> Mon, 15th February 2016:  Extension Joints Sealing
  • Day 117/ 210 Days –> Fri, 12th February 2016:  Top Bricks Clean
  • Day 115/ 210 Days –> Wed, 10th February 2016:  Top Floor Eaves Installed
  • Tue, 9th February 2016:  Received $ Bricks Invoice $
  • Day 110/ 210 Days –>  Fri, 5th February 2016:  Brickwork completion!
  • Thu, 4th February 2016:  Rain Day 😦
  • Day 108/ 210 Days –> Wed, 3rd February 2016:  TV Antenna Installation
  • Day 099/ 210 Days –> Mon, 25th January 2016:  Some Brickwork Activity
  • Fri, 22nd January 2016: Rain Day 😦
  • Day 093/ 210 Days –> Tue, 19th January 2016:  Sand delivery
  • Fri, 15th January 2016:  Rain Day 😦
  • Day 086/ 210 Days –> Tue, 12th January 2016:  1st Floor Terracotta Roof Tiles Completed and more Brickwork
  • Day 083/ 210 Days –> Sat, 9th January 2016:  Brickwork on a Saturday
  • Day 082/ 210 Days –> Fri, 8th January 2016:  More Brickwork
  • Mon – Thu, 4 – 7th January 2016:  Rain Day 😦
  • Day -75/ 210 Days –> Fri, 1st January 2016:  New Years Day Public Holiday
  • Day 072/ 210 Days –> Tue, 29th December 2015:  Whirly Birds are Up!
  • Day 071/ 210 Days –> Mon, 28th December 2015:  Replacement Boxing Day Public Holiday
  • Day 069/ 210 Days –>  Fri, 25th December 2015:  Christmas Day Public Holiday
  • Day 066/ 210 Days –> Wed, 23rd December 2015:  Some Brickwork Progress
  • Tue, 22nd December 2015:  Rain Day 😦
  • Day 064/ 210 Days –> Mon, 21st December 2015:  1st Roof Installation Progress
  • Day 061/ 210 Days –> Fri, 18th December 2015:  1st Floor Terracotta Roof Tiles Installation
  • Day 060/ 210 Days –> Thu, 17th December 2015:  More Bricks and Terracotta Roof Tiles Delivery
  • Day 058/ 210 Days –> Tue, 15th December 2015:  1st Floor Gutter and Fascia 
  • Day 054/ 210 Days –> Fri, 11th December 2015:  Brickwork continues & scaffolding up 
  • Day 053/ 210 Days –> Thu, 10th December 2015:  Brickwork continues & scaffolding delivery
  • Day 052/ 210 Days –> Wed, 9th December 2015:  Houspect Frames Inspection & Brickwork continues
  • Day 051/ 210 Days –> Tue, 8th December 2015: Brickwork continues…
  • Day 050/ 210 Days –> Mon, 07 December 2015:  Bricks laying continued
  • Fri, 4th December 2015:  Received $ Frames Invoice $
  • Day 047/ 210 Days –> Fri, 04 December 2015
    • First line of bricks
    • Completion of Frames & Roof Trusses Installation
  • Day 046/ 210 Days –> Thu, 03 December 2015: Internal plumbing and gas connections and delivery of bricks
  • Day 045/ 210 Days –> Wed, 2 December 2015:  Sand Delivery
  • Tue, 01 Dec’15:  Houspect Frames Inspection booked for Tue, 8th Dec’15 
  • Day 043/ 210 Days –> Mon, 30 November 2015:  First Floor Frames & Roof Trusses Installation Continued
  • Day 041/ 210 Days –> Sat, 28 November 2015:  First Floor Frames Installation Continued:
  • Day 040/ 210 Days –> Fri, 27 November 2015:  Installation of First floor Frames and Windows at the Ground Floor
  • Day 039/ 210 Days –> Thu, 26 November 2015:  Install Windows and Roof Trusses
  • Day 038/ 210 Days –> Wed, 25 November 2015:  First Floor Frames, Windows & Double Stacker Doors Delivery
  • Day 037/ 210 Days –> Tue, 24 November 2015: Ground Floor Frames Installation Continued
  • Day 036/ 210 Days –> Mon, 23 November 2015: Installation of Ground Floor Frames
  • Day 032/ 210 Days –> Thu, 19 November 2015:  Delivery of Frames
  • Day 022-026/ 210 Days –>  Mon – Fri, 9 – 13th November 2015:  Plumbing, Water, Power & NBN Conduits
  • Day 019/ 210 Days –> Fri, 6th November 2015:  Internal/ External Drainage & Portaloo
  • Day 018/ 210 Days –> Thu, 5th November 2015:  Water connection
  • Wed, 4 Nov ’15:  Received Houspect Slab Inspection Report
  • Day 016/ 210 Days –> Tue, 3rd November 2015:  No activity
  • Day 015/ 210 Days –> Mon, 2nd November 2015:  Site Fenced and Houspect slab inspection completed
  • Fri, 30th October 2015: Received $ Slab Invoice $
  • Day 012/ 210 Days –> Fri, 30 October 2015:  SLABBED!
  • Day 011/ 210 Days –>  Thu, 29 October 2015
    • Framework for Slab and pre slab work started
    • Foam, waffle pods & steel currently laid, foundation laid for slab
  • Day 010/ 210 Days –>  Wed, 28 October 2015
    • Meet and greet with Clarendon team:  Construction Area Manager, Site Manager & CSC
  • Day 009/ 210 Days –>  Tue, 27 October 2015:  Plumbing provision laid
  • Day 008/ 210 Days –>  Mon, 26 October 2015:  Pre-slab preparation…
  • 21 October:  Houspect confirmed slab inspection scheduled for Mon, 2nd November 2015.
  • Day 003/ 210 Days –>  Wed, 21 October 2015:  Site piering
  • 20 October: Contacted Houspect to give heads up for slab schedule
  • Day 001/ 210 Days –>  Mon, 19 October 2015:  Site excavation
  • 16 October 2015:  Received 1st $ Invoice $ from Clarendon
  • 15 October 2015:  Received confirmation that our file has been signed off for construction
  • 14 October 2015:  Signed off all documents for construction
  • 13 October 2015:  Received final construction plans, final consolidation (contract tender and post contract variations), Final Colours Selection Schedule, kitchen plans and schedule and reconciliation and progress payment schedule.
  • 09 October 2015:  Site Pegged
  • 07 October 2015:  Signed off plans
  • 07 October 2015:  Received updated floor plans for construction
  • 02 October 2015:  Received updated floor plans for review before we go into construction
  • 02 October 2015:  Received C.D.C. Approval by Local
  • 22 September 2015:  Signed off Construction Loan Documents
  • 17 September 2015:  Construction Loan Approval
  • 17 September 2015:  Development plans have been lodged with CDC (3 weeks estimated processing)
  • 10 August 2015:  Full land settlement
  • 21 July 2015:  Received confirmation from Solicitor from land developer that the land has registered
  • 29 May 2015:  Received advise from Solicitor that land developer has lodged plan for title registration
  • 13 Apr 2015:
    • Clarendon Colour Selection Appointment
    • Electrical Selection Appointment
    • Your Home Kitchens Selection Appointment
  • 23 Mar 2015:  TileDirect Selection appointment
  • 20 Mar 2015:  Clarendon Homes Colour Studio appointment
    1. Colours Appointment (Clarendon)
    2. Aircon
    3. CarpetCall
    4. EHI
    5. Genstairs
    6. Zurcorp
    7. Your Home Kitchens
    8. KMD
  • 28 Feb 2015:  Signing of Contract documents
  • 28 Feb 2015:  Contract appointment with Clarendon Homes Part 2
  • 25 Feb 2015:  Contract appointment with Clarendon Homes Part 1
  • 02 Feb 2015:  Signing of the Tender documents
  • 02 Feb 2015:  Tender appointment with Clarendon Homes Part 2
  • 20 Jan 2015:  Tender appointment with Clarendon Homes Part 1
  • 03 Jan 2015:  Signing of Initial Home & Land Package
  • 29 Dec 2014:  Deposit of $4,000 with Clarendon Homes
  • 27 Dec 2014:  Deposit of $1,000 with Clarendon Homes

————————————

Next activities:

  • Site & House Clean
  • HANDOVER
  • Retaining Wall & Fencing
  • Driveway & pathway concreting
  • Landscaping
  • Window cover installation
  • Move in