Day 247/ 210 (Tue, 21st Jun’16): More Painting & External Window Finishing


Now on Week 36/ out of 30-week contract build, plus the negotiated 3 – 5 weeks in addition from commencement of gyprock (Sat, 2nd Apr’16), @Clarendon_Homes. PCI date moved twice and now scheduled for Fri, 24th Jun’16.

Noted that finally @Clarendon_Homes has completed the finishing on all external windows as well as double stackers and sliding door.  Painting still in full swing, external painting continued and external bed 1 corner window finishing completed.