Day 134 (Mon, 29th Feb’16): Lower Floor Roof Trusses


On the 20th week (out of the 30-weeks) of the @Clarendon_Homes construction build, finally the lower roof trusses have been installed on the garage.  The perimeter fence has not been stripped down yet and is still being supported by one length of wood from falling and smashing into the windows on the right hand side of the… Read More Day 134 (Mon, 29th Feb’16): Lower Floor Roof Trusses

About


We embark in our @Clarendon_Homes dream home building journey between two people with no experience in building a house in this scale our life.  So here goes our journey. After months and months of searching we found a vacant lot and the most suitable home design for our family and chose to build with @Clarendon_Homes. 20 weeks… Read More About

Day 131 (Fri, 26th Feb’16): A Bit Tidier


@Clarendon_Homes tidied the site a bit, all scaffolds that were stripped down from top floor have now been collected.  Unfortunately for us, no other visible construction progress :-(. Spoke to our @Clarendon_Homes Site Manager, progress update this week were: Top floor painting of eaves and downpipes Oxford Facade rendering Stripping of top floor scaffolds Adjust… Read More Day 131 (Fri, 26th Feb’16): A Bit Tidier

Day 130 (Thu, 25th Feb’16): Top Floor Scaffolds Stripped


Nice, went down to the site and glad to see that @Clarendon_Homes was able to finally strip the top floor scaffolds and prepared lower scaffolds for cladding, lower roof trusses, lower floor gutter, fascia and roof tiles installation. @Claredon_Homes is supporting perimeter fence with wood to prevent from leaning into the house – will need… Read More Day 130 (Thu, 25th Feb’16): Top Floor Scaffolds Stripped

Day 124 (Fri, 19th Feb’16): No Activity


No visible sign of construction activity, yet again. Received call from our Clarendon Homes Site Manager and he’s provided the following update: Activities this week Extension joints sealing Downpipes installation on right side of the house Activities from next week: Painting of eaves and downpipes (Mon, 22nd Feb) Strip scaffolding from right side of the… Read More Day 124 (Fri, 19th Feb’16): No Activity