Clarendon Homes Weekly Progress
@Clarendon_Homes Construction Weekly Progress Activities Scheduled for the Week: Now on Week 37/ out of 30-week contract build, plus the negotiated 3 – 5 weeks in addition from commencement of gyprock (Sat, 2nd Apr’16), @Clarendon_Homes has completed the house and will just need to finish issues captured during the practical completion walkthrough to deliver the house. @Clarendon_Homes Handover is scheduled for… Read More Clarendon Homes Weekly Progress