Clarendon Homes Weekly Progress


@Clarendon_Homes Construction Weekly Progress Activities Scheduled for the Week: Now on Week 37/ out of 30-week contract build, plus the negotiated 3 – 5 weeks in addition from commencement of gyprock (Sat, 2nd Apr’16), @Clarendon_Homes has completed the house and will just need to finish issues captured during the practical completion walkthrough to deliver the house.  @Clarendon_Homes Handover is scheduled for… Read More Clarendon Homes Weekly Progress

Timeline


Day 255/ 210 Days –>  Wed, 29th Jun’16:  Clarendon House Handover! Day 254/ 210 Days –> Tue, 28th Jun’16:  Site & House Cleaning, completion of painting and final touches Day 253/ 210 Days –>  Mon, 27th Jun’16:  Installation of appliances (Gas Stove, Rangehood, Microwave and Dishwasher), installation of continuous flow gas system Day 250/ 210… Read More Timeline