Day 165 (Thu, 31st Mar’16): No Activity?


This is our 24th week/ out of 30-week construction contract.  @Clarendon_Homes has negotiated further 2-4 weeks in addition to cover the 5-week shutdown and rain days.  This means there’s only 8 weeks to go to complete everything and get the house ready. Went past the site today and did not see any visible @Clarendon_Homes construction activity/ progress on our house.  Very… Read More Day 165 (Thu, 31st Mar’16): No Activity?

Day 164 (Wed, 30th Mar’16): Fixed Houspect Issues


Received confirmation from @Clarendon_Homes Site Manager that issues raised by @Houspect were addressed today.  The rest will be addressed as construction on the house is progressed. We’re still requesting confirmation from @Clarendon_Homes with regards to the insulation upgrade of R1.5 Glasswool Batts to internal walls of entire first floor.  Based from pictures received from @Houspect and @Clarendon_Homes Site Manager, there… Read More Day 164 (Wed, 30th Mar’16): Fixed Houspect Issues

Day 158 (Thu, 24th Mar’16): Cladding Installation & Gyprock Materials Delivery


Saw this morning that Gyprock Materials has been delivered and brought into the house.  Ecstatic to find out that the long awaiting cladding installation has been finally completed – thanks to our @Clarendon_Homes Site Manager! Also saw that gyprock, cornices and other materials have been delivered! In the weekly update with our @Clarendon_Homes Site Manager, he… Read More Day 158 (Thu, 24th Mar’16): Cladding Installation & Gyprock Materials Delivery

Day 156 (Tue, 22nd Mar’16): Pre-Lining Walkthrough


During the Pre-Lining walkthrough this morning, @Clarendon_Homes has provided an estimate of 8-10 weeks that the house will be completed from Gyprock installation.  Gyprock installation is tentatively booked from Fri, 1st April 2016.  This brings us to an estimated Practical Completion Inspection (PCI)/ Walkthrough between Fri, 27th May to Thu, 9th June 2016.  If all… Read More Day 156 (Tue, 22nd Mar’16): Pre-Lining Walkthrough

Day 155 (Mon, 21st Mar’16): Scaffold Stripped and Site Cleaned


@Clarendon_Homes finally stripped lower floor scaffolds.  Unfortunately, no sign of the cladding being completed.  The perimeter fence precariously leaning towards the house was finally removed.  The site has been cleaned, we’re guessing in preparation for the site visit and meeting with @Clarendon_Homes new Construction Area Manager. We can definitely see the full house now especially… Read More Day 155 (Mon, 21st Mar’16): Scaffold Stripped and Site Cleaned