Day 226/ 210 (Tue, 31st May’16): No Visible Activity 3-Days


Now on Week 33/ out of 30-week contract build, plus the negotiated 3 – 5 weeks in addition from commencement of gyprock (Sat, 2nd Apr’16), @Clarendon_Homes only has less than 2 weeks to finish and deliver the house.  Would be interesting to see if @Clarendon_Homes would be able to meet their timeline – let’s wait and see! Pretty… Read More Day 226/ 210 (Tue, 31st May’16): No Visible Activity 3-Days

Day 220/ 210 (Fri, 27th May’16): Weekly Update from SS


Now on Week 32/ out of 30-week contract build, plus the negotiated 3 – 5 weeks in addition from commencement of gyprock, @Clarendon_Homes only has less than 2 weeks to finish and deliver the house. @Clarendon_Homes Site Manager in his weekly update confirmed the following activities were completed: Electrical Works Completed:  All power points, light points, recessed LED light… Read More Day 220/ 210 (Fri, 27th May’16): Weekly Update from SS

Clarendon Quality Issues Log


In preparation for @Clarendon_Homes Practical Completion Walkthrough, we have noted the list of issues that would need to be addressed and completed before handover. @Clarendon_Homes Site Manager is actively working through each items raised to complete everything before the walkthrough scheduled on Mon, 20th Jun’ 16. Do take note that all these photos were taken with the knowledge of… Read More Clarendon Quality Issues Log

Day 220/ 210 (Wed, 25th May’16): Data & Security


Now on Week 32/ out of 30-week contract build, plus the negotiated 3 – 5 weeks in addition from commencement of gyprock, @Clarendon_Homes only has less than 2 weeks to finish and deliver the house. Another good day today – @Clarendon_Homes completed Data and Security works on the house! Wondering why the Security & Data box was not… Read More Day 220/ 210 (Wed, 25th May’16): Data & Security

Day 219/ 210 (Tue, 24th May’16): Electrical Works Done & Door Handles Installed


Now on Week 32/ out of 30-week contract build, plus the negotiated 3 – 5 weeks in addition from commencement of gyprock,@Clarendon_Homes only has less than 2 weeks to finish and deliver the house. @Clarendon_Homes has completed electrical works today (internal and external light points, exhaust fans installation, smoke alarms, recessed lights installation).  The external laundry door… Read More Day 219/ 210 (Tue, 24th May’16): Electrical Works Done & Door Handles Installed

Day 218/ 210 (Mon, 23rd May’16): Electrical Works & Aircon Ducts


Now on Week 32/ out of 30-week contract build, plus the negotiated 3 – 5 weeks in addition from commencement of gyprock, @Clarendon_Homes only has less than 2 weeks to finish and deliver the house. Glad to see that @Clarendon_Homes has commenced electrical works today.  Noted that power points have been completed and light switches installed.  All aircon… Read More Day 218/ 210 (Mon, 23rd May’16): Electrical Works & Aircon Ducts

Day 215/ 210 (Fri, 20th May’16): External Painting


Now on Week 31/ out of 30-week contract build, plus the negotiated 3 – 5 weeks in addition from commencement of gyprock, @Clarendon_Homes only has than 1 – 3 weeks to finish and deliver the house. @Clarendon_Homes Site Manager in his weekly update confirmed the following activities to be completed: Internal Painting Completed:  All internal walls, skirting, architraves, doors… Read More Day 215/ 210 (Fri, 20th May’16): External Painting

Day 214/ 210 (Thu, 19th May’16): More Painting & Notice of Practical Completion


Now on Week 31/ out of 30-week contract build, plus the negotiated 3 – 5 weeks in addition from commencement of gyprock, @Clarendon_Homes only has less than 1 – 3 weeks to finish and deliver the house. Internal and external painting continued today. There’s still touch up that needs to be done, the pivot door will still… Read More Day 214/ 210 (Thu, 19th May’16): More Painting & Notice of Practical Completion

Day 213/ 210 (Wed, 18th May’16): Painting & Painting & More Painting


Now on Week 31/ out of 30-week contract build, plus the negotiated 3 – 5 weeks in addition from commencement of gyprock, @Clarendon_Homes only has than 1 – 3 weeks to finish and deliver the house. When we went past the site this afternoon, @Clarendon_Homes painters were still at the house and internal painting is still ongoing.  All the walls… Read More Day 213/ 210 (Wed, 18th May’16): Painting & Painting & More Painting

Day 212/ 210 (Tue, 17th May’16): Kitchen Sink, Toilet Suites, Basins, Bath Tub & Plumbing


Now on Week 31/ out of 30-week contract build, plus the negotiated 3 – 5 weeks in addition from commencement of gyprock, @Clarendon_Homes only has less than 1 – 3 weeks to finish and deliver the house. Went past noon today and glad to see that @Clarendon_Homes has installed the undermount kitchen sink!  Noted that all the bathroom basins, bath… Read More Day 212/ 210 (Tue, 17th May’16): Kitchen Sink, Toilet Suites, Basins, Bath Tub & Plumbing