Day 103 (Fri, 29th Jan’16): Front Facade Bricks Progress


Clarendon managed some brickwork activity on the front facade of the house.  The oxford facade is nearly complete with the exception of the middle pier.  There’s also progress on the top floor front facade as well as the front porch.   Such a shame that it rained around after 1:30pm. Clarendon still needs to complete brickwork… Read More Day 103 (Fri, 29th Jan’16): Front Facade Bricks Progress

Rain Days


Log of Rain Days during @Clarendon_Homes Build Wed, 4th November 2015:  9.4mm Thu, 5th November 2015:  19.5 mm Sat, 14th November 2015:  32.6 mm Sun, 15th November 2015:  28.0 mm Mon, 16th November 2015:  10.1 mm Thu, 10th December 2015:  9.8 mm Tue, 22nd December 2015: 37.0 mm Wed, 23rd December 2015:  19.0 mm Mon,… Read More Rain Days